Single lane on Hastings bridge extended by an hour through May 9

Construction crews reduced traffic on the Hastings bridge to one lane for most of the past two weeks as they worked to install a platform beneath the deck to support equipment and workers during the project.

Construction crews reduced traffic on the Hastings bridge to one lane for most of the past two weeks as they worked to install a platform beneath the deck to support equipment and workers during the project.

That work has been delayed by inclement weather and as a result, the bridge will be down to one lane for a little longer, through Friday, May 9.

MnDOT is extending the hours of single-lane traffic across the bridge. It will now be down to a single lane from 8 a.m. to 3 p.m., Monday, May 5 through Friday, May 9.

On Saturday, May 3, the bridge will be down to a single lane from 7 a.m. to 7 p.m.

Beginning the week of May 12 the bridge will be down to one lane 24 hours a day, seven days a week. The 24-hour single-lane restriction is now expected to be lifted by mid-July.