How to build a bridge in three years or less

Email Sign up for Breaking News Alerts

Hastings, 55033

Hastings Minnesota 745 Spiral Boulevard 55033

Steve Kordosky, project manager for the new Hastings bridge and also a Hastings High School graduate, stated at the groundbreaking that he's confident the bridge will be completed by May 31, 2013. Here's a look at how they plan to meet that goal.

Advertisement
Advertisement

September 2010 - Pier work begins on the main span.

October 2010 - Pier and abutment work begins on the north approach.

January 2011 - Pre-construction and visual quality work complete.

April 2011 - Pier and abutment work begins on the south approach. Traffic re-routing near Second St. will continue through September.

June 2011 - Design work completed.

October 2011 - Span work begins on the south approach.

January 2012 - Main span floated in; span work begins on the north approach.

June 2012 - North loop opens to traffic.

July 2012 - Main span opens partially to traffic. Deck removal begins on the old bridge.

January 2013 - Demolition of the old bridge complete.

May 2013 - Work finished on south approach. New bridge fully opens to traffic.